Office relocation — when cabling should happen

Where structured cabling sits in an office move programme: survey, empty build, soft landing, IT cutover and day-one MAC.

Office moves fail cabling when furniture lands before pathways are ready — or when IT cutover assumes labels that were never updated.

Survey old and new

Before demolition or strip-out:

  • Capture what must migrate vs what will be abandoned
  • Photograph panels and legends you still trust
  • Confirm landlord / building rules for risers and out-of-hours

Empty vs soft landing

Empty floor: best window for containment, pulls and certification.
Soft landing / phased: cable ahead of each wave; protect live areas; schedule noisy work outside core hours.

Furniture after permanent links are presented — not the other way around — keeps floor boxes and faceplates intact.

IT cutover

Cutover needs:

  • Legend that matches reality
  • Switch-ready presentation in the comms room
  • A snag list against the original point count

After day one

Expect MAC: desks move, APs shift, meeting rooms change. Budget Moves, Adds & Changes so documentation does not rot in month two.

Next step

Share move dates and drawings via Contact. We will tell you where cabling should sit in your programme — not a generic Gantt fantasy.