Snagging and handover for cabling packages
What “practically complete” means: snag against point count, legends, test results and an O&M minimum IT can use.
Soft completion without usable records is not completion.
Snag against the point count
Every outlet on the schedule should exist, label correctly and — if certification is in scope — pass. Open snags should be listed, not whispered.
Legends and results
Panel legends + test PDFs mapped to IDs. If IDs disagree, fix before sign-off.
O&M minimum
What IT needs next year: schedules, methods used, materials assumptions, contacts for MAC. Photos help; searchable schedules matter more.